Model testing of a pumped hydro-electric scheme, Australia

Model testing of a pumped hydro-electric scheme, Australia

An Australian hydro-electric company engaged an EPC contractor to deliver a Pumped Hydro-Electric Scheme project, including the design works. The hydro-electric company is undertaking a design review prior to finalization of the design and the commencement of construction works. Fichtner attends the pump storage hydro-electric model witness test at the Voith laboratory located in Heidenheim, Germany. The witness test takes four weeks in accordance with the Model Witness Test Program prepared by Voith.

Services

  • Providing daily reports to the client on the activities and findings of the relevant day
  • Attending daily video conferences to present the findings during these meetings